The DESIR-EQUIPEX Program
In
December 2011, the French Ministry of Higher Education and Research allocated 9
M€ to the DESIR-EQUIPEX program within the “http://investissement-avenir.gouvernement.fr/”
call. 8 M€ will be devoted from July 2012 to December 2017 to the construction
of the DESIR beam transport tunnels, to an experimental hall of about 900 m2
built on top of a basement of the same size, and to the implementation of a
beam line between the S3 Low-energy branch facility (S3-LEB)
and the DESIR General Purpose Ion Buncher and cooler
(GPIB) inside the DESIR hall. 1 M€ will be devoted from October 2017 to
December 2019 to the operation of the facility.
Management
The
DESIR-EQUIPEX program objectives were defined in March 2013 in an agreement
signed by GANIL, coordinating the program, and the French National Research
Agency (ANR).
The program involves six French laboratories belonging to the CNRS-IN2P3
and the CEA-DSM
institutes:
-
CEN Bordeaux-Gradignan, CNRS-IN2P3 and University of Bordeaux 1
Scientific coordinator: B. Blank
-
GANIL,
CNRS-IN2P3/CEA-DSM
Scientific coordinator: J.-C. Thomas
-
CIMAP, CEA, CNRS, ENSICAEN and University of Caen Basse-Normandie
Scientific coordinator: E. Balanzat
-
IPHC Strasbourg, CNRS-IN2P3 and
University of
Strasbourg
Scientific coordinator: Ph. Dessagne
-
IPN
Orsay, CNRS-IN2P3
and University of
Paris-Sud 11
Scientific
coordinator: L. Perrot
-
LPC
Caen, CNRS-IN2P3, ENSICAEN and University of Caen
Basse-Normandie
Scientific coordinator: X. Fléchard
The
DESIR-EQUIPEX program will be managed within the framework of a consortium
agreement signed by the six partners of the program. The connexion of the
program to the DESIR Collaboration Council and to the DESIR Steering committee
will be defined in the DEsir Collaboration Agreement
(DECA),
signed in January 2012. Figure 1 shows the DESIR management structure.
Figure 1: DESIR
Management Scheme.
Work package breakdown structure
The DESIR-EQUIPEX program is divided into 7 work
packages, managed by the different partners. A presentation of the different
work packages was given at the DESIR-EQUIPEX
kick-off meeting, held at IPN Orsay on
March 29, 2013.
WP0:
Program coordination - GANIL
Ø Coordination
of the different tasks, organization of collaboration meetings
WP1:
Infrastructure - GANIL
Ø Phase
1: Design and construction of the DESIR beam transport tunnels and of the DESIR
building (experimental hall + basement)
Ø Phase
2: Facility operation
WP2:
Beam lines – IPN Orsay
Ø in
collaboration with GANIL and CEN Bordeaux-Gradignan
Ø Phase
1: Design of the DESIR beam lines, construction and test of a prototype section,
implementation of the beam line from S3-LEB to the DESIR experimental hall
Ø Phase
2: Operation of the DESIR beam lines (GANIL)
WP3:
Identification station – IPHC Strasbourg
Ø in
collaboration with GANIL and LPC Caen
Ø Phase
1: Design and construction of the DESIR identification station.
Ø Phase
2: Operation of the DESIR identification station.
WP4:
General purpose Ion Buncher – GANIL + LPC Caen
Ø Installation
and operation of the GPIB developed at CENBG.
WP5:
Beam line equipment remote control – CEN Bordeaux-Gradignan
Ø Design,
implementation and maintenance of the beam line equipment remote control
Ø in
collaboration with GANIL and IPN Orsay
WP6:
Applications – GANIL + CIMAP
Ø search
for industrial and medical applications, pluridisciplinary
researches
Timeline
The timeline of
the DESIR EQUIPEX Program is displayed in Figure 2. The Program is divided in
two phases, from July 2012 to December 2017 for the first one and from October
2017 to December 2019 for the second one.
The phase 1 of
the DESIR EQUIPEX program consists in (July 2012 -> December 2017):
- The design study of the DESIR beam lines, including the construction and the test of a prototype section: From July 2012 to November 2014,
- the construction of the DESIR beam transport tunnels: From April 2016 to May 2017,
- The construction of the DESIR experimental hall and its basement: From September 2016 to May 2017,
- The implementation of the beam line between the S3-LEB and the DESIR experimental hall: From October 2016 to October 2017,
- The implementation of the main beam line and of the experimental setups inside the DESIR hall: From June 2016 to December 2017.
The phase 2 of
the DESIR EQUIPEX program consists in (October 2017 -> December 2019):
- The commissioning of the beam line between S3-LEB and the DESIR hall: From October 2017 to April 2018,
- The commissioning of the main beam line in the DESIR experimental hall and of the experimental setups: From December 2017 to June 2018,
- The operation of the DESIR facility: From June 2018 to December 2019.
Figure 2: Timeline of the DESIR
EQUIPEX Program.
Manpower involvement
The manpower contribution of the
different partners to the DESIR EQUIPEX Program is detailed in Table 1. It
amounts in total to about 364 men.months over 90
months, corresponding to about 4.2 M€ of manpower costs.
In
summary, the individual contributions of the partners are the following:
GANIL: |
204.3 m.m |
IPNO: |
84.8 m.m |
CENBG: |
29.2 m.m |
IPHC: |
24.1 m.m |
LPC Caen: |
17.0 m.m |
CIMAP: |
4.1 m.m |
Table
1: Manpower contribution of the partners in the DESIR-EQUIPEX Program.